The Chinese and Lao sections of the China-Laos 500-kV power interconnection project were physically connected on Thursday, marking a major step in bringing the project into operation.
A section of the China-Laos 500-kV power interconnection project, Yunnan Province, southwest China, February 5, 2026. /CMG
This is another major project in bilateral cooperation following the construction and operation of the China-Laos Railway.
Spanning a total length of 177.5 km, the transmission line includes a 145-km Chinese section and a 32.5-km Lao section. The infrastructure was funded and constructed by China Southern Power Grid Co., Ltd. and Electricite du Laos Transmission Company Limited.
One of the distinctive construction challenges is that much of the work passes through habitats of wild Asian elephants. Since construction officially began in February 2025, ecological protection and safeguarding the elephants' habitat have been a core project priority.
Once operational, the project is expected to enable a two-way transmission capacity of 1.5 million kW, delivering approximately 3 billion kWh of clean electricity annually.
By extending bilateral physical connectivity from transportation to the energy sector, the project is set to strengthen regional infrastructure connectivity and promote the optimization of the energy mix and clean development.