The second China-made large cruise ship "Adora Flora City" completed water injection from the dock and floated smoothly. The launch operation this time will last for seven days. Subsequently, lifeboat unhooking tests and in-dock tours will be carried out sequentially to verify the performance of the 18 super-large lifeboats and two rescue boats onboard under normal working conditions and emergency situations. It is planned to be officially launched on March 20 and fully enter the system debugging and interior decoration completion stage. The sea trials will commence at the end of May and deliveries will be made before the end of the year.