Largest wind base in China's Xizang sends 1st power to grid at 5,100 meters

CGTN

Provided by China Construction Second Engineering Bureau
Provided by China Construction Second Engineering Bureau

Provided by China Construction Second Engineering Bureau

China's Xizang Autonomous Region switched on the first turbines of its biggest wind farm on Monday, sending power from the 5,100-meter-high Himalayas into the regional grid before winter.

The new power units are part of the 150-megawatt phase-one project at the Qiongjie wind base in Shannan City, southern Xizang. The entire base's planned capacity reaches 500-megawatt – the largest wind base under construction in the region, and the only wind project in the region chosen for a national pilot program by the National Energy Administration.

After its completion, the base is expected to produce 394 million kilowatt-hour a year – power for roughly 175,000 households and about 330,000 tonnes of avoided CO2 emissions. It will also back up the grid during nighttime, when solar output falls to zero, and in the winter, when hydropower is low.

Provided by China Construction Second Engineering Bureau
Provided by China Construction Second Engineering Bureau

Provided by China Construction Second Engineering Bureau

Phase one will see the installation of 24 turbines, each rated at 6.25 MW, on ridges averaging 5,100 meters above sea level, where average wind speeds exceed 8 meters per second. Tower sections weigh up to 101.9 tonnes, blades measure 97.3 meters in length, and the hubs are positioned 113 meters above the ground.

Building at such high altitudes on the plateau poses logistical and physiological challenges. Oxygen levels are just 50% to 60% of those at sea level, temperature swings exceed 20 degrees Celsius, strong gusts can arrive without warning, and the construction season lasts only five months.

Provided by China Construction Second Engineering Bureau
Provided by China Construction Second Engineering Bureau

Provided by China Construction Second Engineering Bureau

Crews set up weather stations to track wind in real time and scheduled crane lifts turbine by turbine, hour by hour, according to Zhang Hailiang, a manager of the project. Last year, engineers here pioneered single-blade hoisting above 5,000 meters, cutting the crane footprint by two-thirds and raising the safe operating wind speed to 10 m/s – a template other high-altitude builders can copy.

The turbines carry an intelligent forecasting system fusing radar, terrain modeling and live turbine data to correct for mountain wind bias, flagging curtailment, blade icing and high-wind shutdowns. Grid-forming battery storage and an expanded 220-kilovolt substation come with them.